Case Study

Sandall

Doncaster - Over Pumping

Exsel Pumps received an enquiry from one of our biggest clients to supply a pumping solution to assist with over pumping of the main incoming sewage line in to Sandall Wwtw in Doncaster. Our customer’s remit was to refurbish and reline the main concrete intake diversion tanks.

The main incoming flow rate into the works fluctuated between 150 and 400 L/sec, this fluctuation depended on time of day and the inclement weather.
As the system was split into two sections – We proposed the supply of 2 x 10” Duty Sewage Submersible pumps, 2 x 12” End suction electric centrifugal pumps and 2 x 12” Diesel driven Betsy pumps as standby units. These pumps were all sized according to the worst-case incoming flow rates and used to contain and divert the flow through various 12” pipelines to various points around the sewage treatment works. With over 250m of 12” rigid and flexible pipe work, 12” Magflow meters and valves to regulate equal flow rates our system successfully bypassed and kept the incoming flow contained whilst the refurbishment went ahead.

Using our 2 fully containerised VSD control systems, the electrically driven pumps ramped up and down as the flow rates fluctuated throughout the day and night. Using a pressure transducer positioned in each incoming sump, these transducers constantly read the liquids level in the sump and relayed this information back to the main PLC. The pumps would maintain the levels via the VSD drive system, and the massive incoming flows were contained.

Our system was powered by combination of Super silent diesel generators, we utilised various 500kva and 300kva gens from a supplier that was local to the installation. Opting for a local generator supplier put everyone at ease, however we also chose this supplier to match our quality and service.

In projects of this nature – quality equipment and back up service is paramount.

Our special project installation team worked tirelessly from the moment the kit arrived on site till the system was up and running. A unique 24/7 project and a very happy client.

This system was in place and operational for 7 weeks and along with our 24/7 on call support we exceeded our customers expectations.

Exsel fleet has “Specialist capability”

The equipment utilised by Exsel on this project was available and ready to be installed by our specialist installations crew, the Exsel fleet has a specialist capability particularly when considering sewage applications. As proven in this application, Exsel has provided solutions and equipment that others have not been able to match.

Services Provided

And more...

See other case studies

Case Studies

Lidl Fire Pump

A high-profile distribution warehouse required a temporary fire pump installation to maintain sprinkler protection while modifications were carried out to the permanent system. ...

Case Studies

Pyro Protection

A site required immediate temporary fire protection capable of delivering 95–100 l/sec at 10 bar to maintain sprinkler coverage while permanent infrastructure was unavailable....

Case Studies

Temporary Fire Pump Protection at Operational Gas Works

A live gas works required its permanent fire pump to be removed for repairs, leaving a critical gap in fire protection. ...

Case Studies

Emergency over pumping solution

Exsel Pumps got that call that we all dread. “We have a major burst pipe line – Please come and help”...

Case Studies

Periodic Storm tank rag-laden material removal

Exsel Pumps was called upon to supply a system that could over pump heavily ragged material from the storm tanks in Crossness STW, which will increase the holding capacity, alleviating the need to discharge into the Thames river....

Case Studies

Canal Bypass Pumping system

Its not just sewage that we love to get involved with – we often have dirty drainage canals that need to be over pumped whilst repair work is being done on these vital canals spread around our country....

Case Studies

River water to Canal transfer

Exsel Pumps was called upon to supply a pump to transfer river water from the River Don to keep the Canal level at a working depth in the centre of Rotherham....

Case Studies

Fareham Emergency

The full installation was carried out by the Exsel Team utilising 450mm diameter flanged steel pipework that provided a secure tamper-proof and leak-free solution. Using this size of pipework reduced the number of pipe runs. The installation Team worked overnight to ensure the over pump capability was set up and ...

Case Studies

Removal Of Chlorinated Water From An Underground Reservoir

In late 2020 Exsel Pumps was requested to remove the highly chlorinated water from an underground reservoir....

Case Studies

Emergency over pumping solution

We were initially requested to supply a few 8” and 12” Diesel driven Betsy pumps – These pumps were used to contain and divert the flow on one of the main inlet pipe lines servicing the sewage treatment works....

Case Studies

Canal Bypass Pumping system.

Its not just sewage that we love to get involved with – we often have dirty drainage canals that need to be over pumped whilst repair work is being done on these vital canals spread around our country. ...

Case Studies

River Overpump for New Bridge Installation

The project was to supply and install two huge submersible/immersible L12K pumps, with each pump capable delivering 1,000 L/sec at a 10 m head. The pipeline consisted of Individual 450mm suction and discharge lines that were installed across the site. At the end of each delivery line, special care ...

Case Studies

East Worthing Storm Pump

Exsel Pumps responded to an emergency request to look at a major problem faced at East Worthing Works. It soon became obvious the scale and complexity of the problem. The initial problem was the failure of the storm pumps for the works and a system had to be put in ...

×