Case Study

Lidl Fire Pump

Problem:

A high-profile distribution warehouse required a temporary fire pump installation to maintain sprinkler protection while modifications were carried out to the permanent system.

The site operated continuously and could not risk a gap in fire cover. The temporary system needed to replicate the existing system and integrate with multiple storage tanks maintaining uninterrupted supply to the sprinkler network all without disrupting warehouse operations.

Solution:

Exsel Pumps delivered and installed a high-pressure temporary pump system designed to mirror the site’s existing configuration. Working alongside the client’s engineering team, we integrated into a newly prepared 12″ flanged connection outside the pump house and constructed a manifold system to manage suction and discharge flows.

Pipework was routed from two storage tanks into a shared suction manifold, with tank 2 drained in advance to allow removal and modification of the gate valve assembly. Re-installed valve and a 90-degree bend ensured compatibility with the temporary layout while preserving operational control.

Discharge from the pump was fed into a second manifold supplying both the sprinkler system and tank refill line, replicating the original system and maintaining safe operational flow.

Once installed, the system was pressure-tested, leak-checked, and commissioned in partnership with site engineers. Exsel provided a full operational demonstration and handover, ensuring the client’s team could safely monitor and manage the temporary installation.

To ensure ongoing performance and compliance, Exsel Pumps carried out scheduled weekly and monthly servicing and testing. Our engineers undertook routine inspections, system checks and performance verifications ensuring the temporary system remained fully operational and compliant throughout the hire period.

Outcome:

The warehouse maintained full sprinkler protection throughout the works with no interruption to operations. The temporary system functioned as a direct substitute for the permanent infrastructure, preserving compliance and operational continuity. The structured handover allowed the client to confidently monitor the installation, ensuring ongoing reliability until permanent upgrades were completed.

Services Provided

And more...

See other case studies

Case Studies

Pyro Protection

A site required immediate temporary fire protection capable of delivering 95–100 l/sec at 10 bar to maintain sprinkler coverage while permanent infrastructure was unavailable....

Case Studies

Temporary Fire Pump Protection at Operational Gas Works

A live gas works required its permanent fire pump to be removed for repairs, leaving a critical gap in fire protection. ...

Case Studies

Sandall

Exsel Pumps received an enquiry from one of our biggest clients to supply a pumping solution to assist with over pumping of the main incoming sewage line in to Sandall Wwtw in Doncaster. ...

Case Studies

Emergency over pumping solution

Exsel Pumps got that call that we all dread. “We have a major burst pipe line – Please come and help”...

Case Studies

Periodic Storm tank rag-laden material removal

Exsel Pumps was called upon to supply a system that could over pump heavily ragged material from the storm tanks in Crossness STW, which will increase the holding capacity, alleviating the need to discharge into the Thames river....

Case Studies

Canal Bypass Pumping system

Its not just sewage that we love to get involved with – we often have dirty drainage canals that need to be over pumped whilst repair work is being done on these vital canals spread around our country....

Case Studies

River water to Canal transfer

Exsel Pumps was called upon to supply a pump to transfer river water from the River Don to keep the Canal level at a working depth in the centre of Rotherham....

Case Studies

Fareham Emergency

The full installation was carried out by the Exsel Team utilising 450mm diameter flanged steel pipework that provided a secure tamper-proof and leak-free solution. Using this size of pipework reduced the number of pipe runs. The installation Team worked overnight to ensure the over pump capability was set up and ...

Case Studies

Removal Of Chlorinated Water From An Underground Reservoir

In late 2020 Exsel Pumps was requested to remove the highly chlorinated water from an underground reservoir....

Case Studies

Emergency over pumping solution

We were initially requested to supply a few 8” and 12” Diesel driven Betsy pumps – These pumps were used to contain and divert the flow on one of the main inlet pipe lines servicing the sewage treatment works....

Case Studies

Canal Bypass Pumping system.

Its not just sewage that we love to get involved with – we often have dirty drainage canals that need to be over pumped whilst repair work is being done on these vital canals spread around our country. ...

Case Studies

River Overpump for New Bridge Installation

The project was to supply and install two huge submersible/immersible L12K pumps, with each pump capable delivering 1,000 L/sec at a 10 m head. The pipeline consisted of Individual 450mm suction and discharge lines that were installed across the site. At the end of each delivery line, special care ...

Case Studies

East Worthing Storm Pump

Exsel Pumps responded to an emergency request to look at a major problem faced at East Worthing Works. It soon became obvious the scale and complexity of the problem. The initial problem was the failure of the storm pumps for the works and a system had to be put in ...

×