Case Study

Fareham Emergency

Cost-Effective Emergency Raw Rag-Laden Sewage Over-Pump

Exsel Pumps was called upon in an emergency to supply a system that could over pump a large collapsed sewer main in Fareham. Initially, the contractor was looking at a submersible pump option, but Exsel proposed a more cost effective option utilising electric driven surface mounted immersible pumps with stand-alone vacuum priming systems. This negated the need to build a suction sump for the submersible units which would have cost more money and time—considering also the urgent nature of the project where houses nearby would have been in danger of a sewage overspill. Instead the selected option was to cut two saddles in the existing pipe where Exsel would position suction pipework directly into the line. This also reduced the environmental impact due to odour compared to a large suction sump.

Two 16” (400mm) pumps with 18” (450mm) discharge pipe were utilised each capable of 3,000 m3/h (830 l/s) with unrivalled rag handling capability as necessitated. In addition, a back-up 12” Betsy diesel pump was supplied to provide additional standby capability. With a suction lift of about 6 metres the pumps were controlled by a PLC container on variable speed drives with level control probes. Each pump was capable of the predicted maximum flow but it was decided due to the critical nature of the project that both pumps should be running and the level sensing would ramp up the speed of the pumps as the flow conditions increased. This provided a better safety factor considering the wide variance of flows and the proximity of a nearby residential area. Utilising two units of this size reduced the need to operate a higher quantity of smaller pumps offered by competitors which would have required more room on site with more pipe runs and more power requirement.

So critical was the nature of the project that Exsel also installed an SMS system that contacted it’s engineers in the event of any alarms. Exsel therefore also providing 24/7 back-up to the application.

Services Provided

And more...

Exsel the Complete Solution Provider

The full installation was carried out by the Exsel Team utilising 450mm diameter flanged steel pipework that provided a secure tamper-proof and leak-free solution. Using this size of pipework reduced the number of pipe runs. The installation Team worked overnight to ensure the over pump capability was set up and running in the quickest timescale but also in the safest manner.

See other case studies

Case Studies

Lidl Fire Pump

A high-profile distribution warehouse required a temporary fire pump installation to maintain sprinkler protection while modifications were carried out to the permanent system. ...

Case Studies

Pyro Protection

A site required immediate temporary fire protection capable of delivering 95–100 l/sec at 10 bar to maintain sprinkler coverage while permanent infrastructure was unavailable....

Case Studies

Temporary Fire Pump Protection at Operational Gas Works

A live gas works required its permanent fire pump to be removed for repairs, leaving a critical gap in fire protection. ...

Case Studies

Sandall

Exsel Pumps received an enquiry from one of our biggest clients to supply a pumping solution to assist with over pumping of the main incoming sewage line in to Sandall Wwtw in Doncaster. ...

Case Studies

Emergency over pumping solution

Exsel Pumps got that call that we all dread. “We have a major burst pipe line – Please come and help”...

Case Studies

Periodic Storm tank rag-laden material removal

Exsel Pumps was called upon to supply a system that could over pump heavily ragged material from the storm tanks in Crossness STW, which will increase the holding capacity, alleviating the need to discharge into the Thames river....

Case Studies

Canal Bypass Pumping system

Its not just sewage that we love to get involved with – we often have dirty drainage canals that need to be over pumped whilst repair work is being done on these vital canals spread around our country....

Case Studies

River water to Canal transfer

Exsel Pumps was called upon to supply a pump to transfer river water from the River Don to keep the Canal level at a working depth in the centre of Rotherham....

Case Studies

Removal Of Chlorinated Water From An Underground Reservoir

In late 2020 Exsel Pumps was requested to remove the highly chlorinated water from an underground reservoir....

Case Studies

Emergency over pumping solution

We were initially requested to supply a few 8” and 12” Diesel driven Betsy pumps – These pumps were used to contain and divert the flow on one of the main inlet pipe lines servicing the sewage treatment works....

Case Studies

Canal Bypass Pumping system.

Its not just sewage that we love to get involved with – we often have dirty drainage canals that need to be over pumped whilst repair work is being done on these vital canals spread around our country. ...

Case Studies

River Overpump for New Bridge Installation

The project was to supply and install two huge submersible/immersible L12K pumps, with each pump capable delivering 1,000 L/sec at a 10 m head. The pipeline consisted of Individual 450mm suction and discharge lines that were installed across the site. At the end of each delivery line, special care ...

Case Studies

East Worthing Storm Pump

Exsel Pumps responded to an emergency request to look at a major problem faced at East Worthing Works. It soon became obvious the scale and complexity of the problem. The initial problem was the failure of the storm pumps for the works and a system had to be put in ...

×